宝马项目化流程标准(BMW ABC flyer requirement) 体系要求(宝马项目管理流程)

宝马项目化流程标准全解析(BMW ABC flyer requirement)

ABC flyer/ BMWQMT build phase requirement

宝马的项目流程标准叫做ABC flyer,也叫QMT build phase requirement.为什么叫这么名字,是因为宝马项目的产品零件分为几个阶段:A-samples, B-samples,C-samples, initial-samples.

阶段为: MTBàBBGàPVL/VS0àVS1àVS2àAPàSOP

ABC samples的具体含义请参考下文图片

对于项目的各个阶段标准,最主要的就是MTB和BBG阶段可以提供手工样件prototype, 可以开软模具,此阶段在德国慕尼黑研发FIZ中心装车,主要用于验证设计design.

PVL/VS0阶段一定要量产模具,量产工装,生产产地为中国宝马BBA进行装车。

具体各个阶段的详细标准要求,请看下文解析:

PVL/ VS0:

100% ok parts in terms ofSC/CC, FMK, Gap plan.

100%合格产品,满足特殊特性,重要特性,FMK公差尺寸要求,间隙面差要求。

Tooling:(模具工装)

– All series tools100% ready at tool maker with all functions

所有量产模具和工装要做好,满足所有功能

– Trial out at tool shop T0 – first function test of the tool with parts

模具T0试模满足所有功能要求

– Quality loops (1 – 2) implementation for all tools

质量提升1-2轮对于所有模具

– Trial out at tool shop T1- first part production run with BMW

首次模具T1运行生产邀请BMW

– Further optimization of tooling as necessary

模具进一步优化

– Parts can be produced attool maker for VS0(1)

VS0的零件可以在tool maker进行生产

Production equipments:(生产设备)

– fixtures and assembly supports at series location

工装设备在量产产地

– Series production equipment can be at supplier (prepare Cmk studies)

准备设备的CMK数据研究

– VS(0) parts can be made at equipment supplier

VS0的产品可以在设备厂家生产

(Except some special part families e. g. safety relevant parts)

安全件除外

Checking fixtures/Gauges:(检具)

-100 % ready at tool maker or series location

100%状态的检具在tool maker或者

– CMM machine available at series location

三坐标在量产地投入使用

– 100% measurement of all VS(0) parts according to BMW Messplan

VS0产品要100%满足BMW测量要求

– 100% Significant characteristics/Critical Characteristics measured andconfirmed

100%控制特殊特性和重要特殊

Packaging:(包装)

-Temporary packaging defined and agreed by BMW QMT

临时包装方案经过QMT的批准

– Label requirement according to BBA

标签要求满足要求

Additional preventiveQ-planning activities:(额外的质量规划)

-Validation plan agreement

产品PV验证计划

– PFMEA for all production steps

所有工艺步骤的PFMEA

– Definition of production layout at series location with line balancing

生产工艺布局和线平衡

– Control plan according to component specific key characteristics (SC/CC)

控制计划要根据SC/CC来制定

– Forecast production planning and capacity investigation

生产规划和产能调查

– Supply chain concept and backup plan

供应链concept和应急计划

– Quality loops – as much as possible & as independent as possible

质量提升环

VS1:

Parts quality: (零件质量)

100% ok for dimensions (according to BMW messplan), appearance, functionand SC/CC or gap plan relevant characteristics.

100%满足尺寸,外观,功能SC/CC,间隙面差要求。

Tooling:(模具工装)

– All series tools100% ready at series location

所有模具量产工装,量产产地

(Except tools with graining)(皮纹模具除外)

– Machines for series production are defined

定义系列化生产设备

– Process parameter defined and controlled

过程参数定义可控

– Parts must be produced at series location for VS1

VS1零件一定在量产产地生产

Production equipment:(生产设备)

-Series production equipment at final location

量产设备在最终产地

– Assembly line setup 100% done

装配线100%做好

– Poka Yoke 100% working

防错100%工作

– VS1 must are produced at series location

VS1零件一定在量产产地生产

Checking fixtures/gauges andCMM:(检具和三坐标)

-100 % ready at series location

100%在量产产地做好

– SPC definition and labor capacity ready

定义SPC和劳动力产能

Packaging & logistic:(物流包装方案)

-Use temporary packaging as before

临时包装方案

– Series packaging defined and prototype bin confirmed

量产包装方案确认,箱子确认

– IT connection with BBA/BMW installed and working

与BBA确认EDI的IT连接,用于后续接订单

– JIS/JIT Forecast available

拿到BBA的call offs订单预测

Additional preventiveQ-planning activities:(额外的质量规划)

-Parts flow optimization

工艺流程优化

– Visual management/KPI tracking at Shop floor

建立车间的KPI

– Quality training for all operators according to BMW group

对于所有操作工的质量培训

Standards and specifications

– Problem solving process/reaction time

问题解决和反应时间

VS2:

Premise:(前提)

– VS2 parts have to be produced from official BMW processSeries (PZS)!

– Target is to reach PZS green right first time!!!

VS2零件一定要产于PZS审核

目标是一次性到达PZS审核绿色状态

Parts quality: (零件质量)

100% ok for dimensions (according to BMW messplan), appearance,

function and SC/CC or gap plan relevant characteristics.

100%满足尺寸,测量,外观,功能,SC/CC,面差缝隙要求。

Process Series (PZS):(PZS过程审核)

– All tools and equipment are ready

所有的工装模具做好

– All processes from incoming until shipment are linked

所有的过程从来料检验到发货链接在一起

– Quantity: one shift production!

数量:一个班次生产

– Adjustment of the production plan accordingly

可以适当调整生产计划

– Dummy call off for JIS/JIT is needed when the real call off is notenough

如果正式的call offs订单不足,通过创建Dummy order来做PZS审核

– Targets have to be reached (right first time, scrap rate, rework rate,internal PPM, tact time etc)

目标满足(一次性通过率,报废率,返工率,内部PPM,节拍等)

– Quality standard/mindset/knowledge for all operators at all processsteps 100% given

质量标准,意识,知识要灌输到100%工艺步骤中去

– All produced parts should be checked 100% in terms of dimensions,functions and

appearance Ppk ≥ 1.67

所有生产的零件要百检,满足尺寸,功能,外观,PPK大于1.67

– Series packaging available for PZS parts

量产包装对于PZS的零件

– Traceability established and documented

追溯系统建立起来并且文件存档

– Safety stock management

建立安全库存

AP/SOP:

Further steps:

Process series Follow up:

PZS后续问题的跟踪

– Status follow up with actions and timing

后续问题的跟踪和时间节点

– Define next process checks if needed

如果必要定义后续的过程审核

– All required documentations and reports have to be provided to BMW QMTand relevant persons

所有需求的文件要提交给BMW QMT

– Preparation of ISIR yellow status in the RMT/IPQ system

ISIR yellow状态的文件要提交到BMW IPQ系统

– Release ISIR status yellow by QMT (part payment of the tools!)

QMT放行yellow状态的ISIR(部分付款模具)

– Further training of operators and quality persons

进一步培训操作者和质量人员

SOP 3months ramp up:

Ramp up and stabilization:(爬坡和稳定化过程)

– Documentation of SPC data for all component special characteristics

数据记录SPC对于SC特性

– Long term process capability has to be reached to Cpk ≥ 1.33

CPK大于1.33

– By deviations additional quality gates with clear description must beinstalled.

如果有偏差需要建立额外的质量门

Second/Third shiftimplementation:(实施第二和第三班次)

– Hiring qualified operators in suitable time window

出示招聘计划

– Set up training program and follow up

培训计划

– Process checks with 2. or 3. Shift

过程审核第二和第三个班次

– Final BMW process series PZS for new shifts

新的班次的PZS审核

ISIR1 (Production release):

– Providing the Cpk data to BMW QMT

提供CPK数据给QMT

– Release ISIR green status by QMT (rest payment of the tools!)

QMT放行ISIR绿色状态(模具剩余部分的付款)

Series activities:(系列化生产活动)

– Phase out of project teams

项目组退出

– 8D report, PPM monitoring, internal PPM monitoring

8D报告,PPM监控,内部PPM监控

– Additional quality gates for ramp up: GP12, BMW specific q-Gates etc…

爬坡的额外质量门:GP12,特殊质量门等

– Sub supplier monitoring with escalation activities

下级供应商监控和升级活动

宝马项目化流程标准(BMW ABC flyer requirement) 体系要求(宝马项目管理流程)

版权声明:本文内容由互联网用户自发贡献,该文观点仅代表作者本人。本站仅提供信息存储空间服务,不拥有所有权,不承担相关法律责任。如发现本站有涉嫌抄袭侵权/违法违规的内容, 请发送邮件至 举报,一经查实,本站将立刻删除。

(0)
上一篇 2024年2月17日 上午10:47
下一篇 2024年2月17日 上午11:03

相关推荐